Today's Headlines - 03 September 2023
Largest indigenously developed N-plant starts ops
GS Paper - 3 (Energy)

The third unit of the indigenously developed 700-megawatt electric (MWe) nuclear power reactor at the Kakrapar Atomic Power Project (KAPP3) in Gujarat has commenced operations at full capacity. This comes a little over three years since the unit achieved its ‘first criticality’ – a technical term that signifies the initiation of a controlled, but sustained nuclear fission reaction – in July 2020. On 30 June this year, the unit had started commercial operations.

More about the News

In India’s civilian nuclear programme, this is seen as a landmark event, given that KAPP-3 is the country’s first 700 MWe unit and the biggest indigenously developed variant of the Pressurised Heavy Water Reactor (PHWR).
The PHWRs, which use natural uranium as fuel and heavy water as moderator, constitute the mainstay of India’s nuclear power fleet.
Till now, the biggest reactor of indigenous design was the 540 MWe PHWR, two of which have been deployed in Tarapur, Maharashtra.
For India, the operationalisation of its first 700MWe reactor is a significant scale up in technology, both in terms of the optimisation of its PHWR design — the new 700MWe unit addresses the excess thermal margins and also marks an improvement in the economies-of-scale, without significant design changes to the 540 MWe reactor.
Flashback

As India works to ramp up its existing nuclear power capacity of 7,480 MWe to 22,480 MWe by 2031, the 700MWe capacity would constitute the biggest component of this expansion plan. Currently, nuclear power capacity constitutes around 2 per cent of the total installed capacity of 4,17,668 MW (May 31).
Significantly, as India’s civilian nuclear sector gears up to its next frontier — building a 900 MWe Pressurised Water Reactors (PWRs) of indigenous design – the experience of executing the larger 700MWe reactor design would come in handy, especially with respect to the improved capability of making large-size pressure vessels, alongside India’s own isotope enrichment plants being developed to supply a part of the required enriched uranium fuel to power these new generation reactors over the next decade or so, according to DAE officials.
The first ‘pour of concrete’ for laying the foundation of KAPP-3 happened in November 2010 and this unit was originally expected to be commissioned in 2015.

#upsc #news #headline #largest #indigenously #devloped #Nplant #energy #megawatt #kakrapar #atomic #powerproject #gujarat #firstcriticality #india #civilian #nuclear #programme #heavywater #PHWR #tarapur #capacity #pour #concrete #DAE #uranium #fuel #maharashtra #moderator #fission #first #initiation #thirdunit #electric #landmark #pressurised #thermal #margins #economies #november